Critical Path Analysis
A project's activities and their dependencies form a network. A forward pass gives earliest times, a backward pass latest times. Activities with zero total float form the critical path, whose length is the minimum project duration. Total float latest finish earliest start duration. A lower bound for workers is .
Learning objectives
- Draw activity networks from precedence tables (with dummies where needed).
- Find early and late times, the critical path and floats.
- Draw Gantt charts and resource histograms; find a lower bound for workers.
To make breakfast you boil the kettle (3 min), make toast (4 min) and butter it after it's toasted (1 min). What's the shortest time?
Core idea
Foundations before walls, walls before roof; but plumbing and electrics can run at the same time. Some tasks can slip without delaying the move-in date; others can't. Critical path analysis finds which.
Forward pass (max) gives earliest event times; backward pass (min) gives latest. Activities with zero total float form the critical path, and its length is the project's minimum duration.
1. Early and late times
Activities: A(3), B(4), C(2) after A, D(5) after A and B, E(3) after C and D.
Find the duration, critical activities and floats.
- Goal
- Duration and floats.
- Strategy
- Max forwards, min backwards.
- D waits for both A and B.
- E waits for C and D.
- C only needs to finish by E's start.
- A must be done for D at 4.
- where
- float
- how long the activity can be delayed without delaying the project.
2. Resources
- Each activity needs one worker for its duration.
- workers over days provide at most worker-days.
- Round up.
From data to schedule.
If C takes 6 days instead of 2, what changes?
Summary
- Forward: max; backward: min.
- Critical: zero float.
- Workers .
- Critical path
- Longest chain of activities; sets the duration.
- Total float
- Possible delay without delaying the project.
- Gantt chart
- Bar chart of activity timings.
Key formulae
Worked examples
Explore the graph
- Workers needed if everything starts as early as possible: 2 until time 5, then 1.
- The line at is the average workload: at least 2 workers are needed.
Total activity time over days.
Common mistakes
Activity with float 0
Me with no time to spare all week.
Exam tip
Guided practice
Practice questions
More questions on every skill in this subtopic are in the question bank under Practise.
Challenge
Summary
- Forward pass: max.
- Backward pass: min.
- Critical: zero float.
- Workers .
Quick quiz
Same topic, different board
- Specification
- A level Further Mathematics 9FM0
- Where
- Decision 1 · Critical path analysis
- Expected
- Activity-on-arc networks with dummies; early and late event times; critical activities; total float; Gantt (cascade) charts; resource histograms; lower bound for workers; scheduling.
- Calculator
- Permitted; show enough working to earn the method marks.
- Typical style
- Edexcel often opens with a routine part and builds to a "show that" or "prove" part.
- Open in
- YMA01 · WDM119FM0 · Option
Past paper questions
No past paper questions are tagged to this subtopic yet. We add papers every week.