Critical path analysis

1 subtopic≈ 50 min in total
  1. Activity networks and critical paths

    A project's activities and their dependencies form a network. A forward pass gives earliest times, a backward pass latest times. Activities with zero total float form the critical path, whose length is the minimum project duration. Total float == latest finish −- earliest start −- duration. A lower bound for workers is ⌈total activity timeduration⌉\left\lceil\frac{\text{total activity time}}{\text{duration}}\right\rceil.