Activity networks and critical paths
A project's activities and their dependencies form a network. A forward pass gives earliest times, a backward pass latest times. Activities with zero total float form the critical path, whose length is the minimum project duration. Total float = latest finish − earliest start − duration. A lower bound for workers is ⌈durationtotal activity time⌉.