PractiseQuestion bank
Original exam-style questions, mapped to your syllabus. Answers are checked for mathematical equivalence and every attempt updates your mastery.
Sign in to check answers. Your attempts build your mastery and error book.
12 questions
SA-DM-CP-Q011 markL1 FoundationNon-calculatorCritical path
A critical activity is one that
Salam Academy Original Practice · Proposed mark scheme
SA-DM-CP-X041 markL1 FoundationNon-calculatorCritical path
For the same project, find the earliest start time of E.
Salam Academy Original Practice · Proposed mark scheme
SA-DM-CP-X061 markL1 FoundationNon-calculatorNetworks
In an activity-on-arc network, a dummy activity
Salam Academy Original Practice · Proposed mark scheme
SA-DM-CP-0012 marksL2 StandardNon-calculatorCritical path
Find the total float of activity C.
Salam Academy Original Practice · Proposed mark scheme
SA-DM-CP-0032 marksL2 StandardNon-calculatorScheduling
Each activity needs one worker. Find a lower bound for the number of workers needed to finish in 12 days. Salam Academy Original Practice · Proposed mark scheme
SA-DM-CP-G012 marksL2 StandardNon-calculatorCritical path
Activities: A(3), B(4), C(2) after A, D(5) after A and B, E(3) after C and D. Find the minimum project duration.
Salam Academy Original Practice · Proposed mark scheme
SA-DM-CP-X012 marksL2 StandardNon-calculatorCritical path
A(4), B(6), C(3) after A, D(5) after A, E(2) after B and C, F(4) after D and E. Find the minimum project duration.
Salam Academy Original Practice · Proposed mark scheme
SA-DM-CP-X022 marksL2 StandardNon-calculatorCritical path
For the same project, find the total float of activity B.
Salam Academy Original Practice · Proposed mark scheme
SA-DM-CP-X032 marksL2 StandardNon-calculatorScheduling
Each activity needs one worker. Find a lower bound for the number of workers to finish in 13 days. Salam Academy Original Practice · Proposed mark scheme
SA-DM-CP-X051 markL2 StandardNon-calculatorCritical path
For the same project, find the total float of activity D.
Salam Academy Original Practice · Proposed mark scheme
SA-DM-CP-0022 marksL3 ExamNon-calculatorCritical path
Find the total float of activity A.
Salam Academy Original Practice · Proposed mark scheme
SA-DM-CP-0042 marksL3 ExamNon-calculatorCritical path
Activity B is delayed by 2 days. Find the new minimum duration. Salam Academy Original Practice · Proposed mark scheme